← Back to investigation
Technical Analysis

Reverse-Engineering the Ridgeline Emissions Profile

Using EPA AP-42 emission factors, Clean Air Act thresholds, and publicly available data. All calculations shown. February 2026.

Executive Summary

Based on standard engineering calculations, a 785 MW natural gas power plant operating continuously cannot be classified as a minor source of air pollution. Even with the best commercially available emission controls, the facility exceeds the 100 TPY major source threshold for four of six criteria pollutants.

The permit's claimed 99 TPY NOx — precisely 1 ton below the threshold — would require operating at only 27.5% of capacity. The claimed 56 TPY CO would require only 11.5% of capacity. Neither is consistent with powering a 24/7 data center.

1. What Makes a "Major Source"?

Under the Clean Air Act's Prevention of Significant Deterioration (PSD) program, a major source is any facility that emits — or has the potential to emit — 100 tons per year (TPY) or more of any regulated pollutant.

The Ridgeline facility's heat input (~7,458 MMBtu/hr) is 29.8 times the threshold for listed source categories. Whether classified as listed or unlisted, it exceeds all applicable thresholds.

PollutantMajor Source ThresholdPSD Significant Level
NOx100 TPY40 TPY
CO100 TPY100 TPY
SO₂100 TPY40 TPY
PM₁₀100 TPY15 TPY
PM₂.₅100 TPY10 TPY
VOC100 TPY40 TPY

Class I Wilderness Areas

Dolly Sods Wilderness is approximately 10–15 miles from the proposed site. Otter Creek Wilderness is approximately 20–30 miles away. Both are mandatory Class I federal areas under the Clean Air Act — they receive the most stringent air quality protection available.

Any new major source within ~31 miles of a Class I area must demonstrate it won't degrade air quality there. Under the minor source permit, none of this analysis was required.

2. Power & Fuel Calculations

Known Facts (Public Record)

ParameterValueSource
Permitted capacity785 MWWV DEP permit
Diesel backup storage30 million gallonsWVPB, June 2025
Site size~500 acres (up to 10,000)Multiple sources
FuelNatural gas pipelinePermit application

Heat Input & Fuel Consumption

Using a conservative heat rate of 9,500 Btu/kWh (favorable to the applicant — many industrial turbines run 10,000–11,500):

Heat Input = 785,000 kW × 9,500 Btu/kWh = 7,457.5 MMBtu/hr

Annual (24/7): 7,457.5 × 8,760 hr/yr = 65,327,700 MMBtu/yr

Natural gas: ~64 billion scf/yr (~175 million scf/day)

3. Emissions Calculations

Using EPA AP-42, Section 3.1 (Stationary Gas Turbines) — the standard reference for air quality permitting:

785 MW — Best Available Controls (DLN + SCR + Oxidation Catalyst)

This is the most favorable scenario possible for the applicant:

PollutantFactor (lb/MMBtu)Annual EmissionsThresholdResult
NOx0.011359 TPY100 TPY3.6× OVER
CO0.015490 TPY100 TPY4.9× OVER
PM₁₀/PM₂.₅0.0066216 TPY100 TPY2.2× OVER
SO₂0.0034111 TPY100 TPY1.1× OVER
VOC0.002169 TPY100 TPYBelow

Four of five criteria pollutants exceed the major source threshold even with the best available controls. Without controls, NOx alone hits 10,452 TPY — over 100× the threshold.

Even at 200 MW — Still Over

Even a facility only 25% the size of what's permitted would exceed thresholds:

Pollutant200 MW (Best Controls)ThresholdResult
NOx91.5 TPY100 TPY⚠️ Marginal
CO125 TPY100 TPY1.25× OVER
PM₁₀/PM₂.₅55 TPY100 TPYBelow
SO₂28 TPY100 TPYBelow

4. The Permit's Numbers Don't Add Up

The permit reportedly claims 99 TPY NOx and 56 TPY CO. Let's reverse-engineer what operating conditions that requires:

To achieve 99 TPY NOx (with best controls):

99 tons = 198,000 lb/yr
198,000 ÷ 0.011 lb/MMBtu = 18,000,000 MMBtu/yr allowed
At 7,457.5 MMBtu/hr full load:
  18,000,000 ÷ 7,457.5 = 2,414 hours/yr at full load

Running 24/7 (8,760 hr/yr):
  Average load = 18,000,000 ÷ 8,760 = 2,055 MMBtu/hr
  = 216 MW average
  = 27.5% of 785 MW capacity

To achieve 56 TPY CO (with best controls):

56 tons = 112,000 lb/yr
112,000 ÷ 0.015 lb/MMBtu = 7,466,667 MMBtu/yr
Running 24/7:
  Average load = 852 MMBtu/hr = ~90 MW
  = 11.5% of 785 MW capacity

The fundamental question:

Why build a 785 MW power plant if you can only run it at 11–27% capacity?

If the actual power demand is only 90–216 MW, there is no engineering reason to permit 785 MW of capacity. The disparity suggests the facility intends to operate at higher loads than the emission limits would allow.

5. What "Synthetic Minor" Avoids

By classifying as a minor source, the Ridgeline facility bypasses every major protection the Clean Air Act provides for communities near large pollution sources:

RequirementMajor SourceMinor Source (Ridgeline)
Air quality dispersion modeling✅ Required❌ Not required
Class I area impact analysis✅ Required❌ Not required
Federal Land Manager review✅ Required❌ Not required
Visibility impact assessment✅ Required❌ Not required
BACT determination✅ Required❌ Not required
Continuous emissions monitoring✅ Required❌ Not required
Pre-construction air monitoring✅ Required❌ Not required

You are pretending here that you can actually demonstrate that you will be below the major source threshold, even on the best of times, even if you have continuous monitoring. And here you don't even have that. You're truly flying blind.

— Dr. Ron Sahu, expert witness testimony, December 2025

6. Class I Area Impacts

Every criteria pollutant exceeds the PSD significance level that would trigger mandatory Class I area analysis:

PollutantPSD Significant Level785 MW (Best Controls)Multiple
NOx40 TPY359 TPY
PM₂.₅10 TPY216 TPY22×
PM₁₀15 TPY216 TPY14×
SO₂40 TPY111 TPY2.8×
CO100 TPY490 TPY4.9×
VOC40 TPY69 TPY1.7×

Dolly Sods and Otter Creek are among the most pristine wilderness areas in the eastern United States. The minor source classification means no one has modeled what 359 tons/year of NOx and 216 tons/year of particulate matter would do to their air quality.

7. What We Didn't Include

This analysis is conservative — it consistently uses assumptions favorable to the applicant:

Methodology

This analysis uses:

The methodology is consistent with standard air quality engineering practice. All calculations are shown. Corrections and additional data are welcome.

A 785-megawatt natural gas power plant cannot be a minor source of air pollution.

This is not a close call.

← Back to investigation